Kehl St Fall Build 2022
Habitat for Humanity: Kitchener Waterloo Ontario Canada
Thursday, February 26, 2015
just some final touches for the drywall
completing the firewall
a bit of outside work
getting the basements ready for some concrete
Tuesday, February 24, 2015
drywalling
bulkheads
a little to far to the right
Monday, February 23, 2015
more drywalling
the start of the bulkheads
getting close to finishing the bottom floor
Thursday, February 19, 2015
drywalling as usual
finishing the first unit
closing in on getting the upstairs of the third unit done
getting the heating ducts ready
Wednesday, February 18, 2015
a half day of drywalling
the afternoon spent curling
look at this shot
well this one not so good
Tuesday, February 17, 2015
Another good day of drywalling. Ceilings are done upstairs in center unit and walls are started.
Call is in for insulation in the ceiling
Thursday, February 12, 2015
dry walling the bulkheads
putting in the bollards so the snow blowing person doesn't hit the electrical box
nailing in the fire stops
Wednesday, February 11, 2015
more bulkheads
making sure everything is sealed up
making sure all the insulation is done
Tuesday, February 10, 2015
closing in the bulkheads
getting the next house ready for drywalling
installing the heating pipes